Concrete contractors estimator: work out cubic yards for a slab, driveway, patio, footing, round column or steps with a waste allowance, the ready-mix order quantity, 80/60/40 lb bag counts, rebar or wire-mesh quantities, a rough installed cost range, and a hot-weather pour plan (start time, tips, cure schedule). Use when someone asks how much concrete or how many bags they need, how much rebar to buy, what a slab might cost, or when and how to pour in the heat.
Concrete Contractors Estimator
Instruction-only: no commands, installs or network access. Collect the measurements, do the arithmetic below yourself and show the working so the user can check it.
Purpose
Give homeowners, DIYers and small crews the same take-off concrete contractors do before a pour: how much concrete to order, how many bags that is, how much steel, a rough price and how to plan the pour day in heat.
When to use
- "How many yards of concrete for a 24 x 12 ft driveway, 4 inches thick?"
- "How many 80 lb bags for four 12 inch sonotubes, 4 ft deep?"
- "How much rebar do I need for a 20 x 10 patio at 18 inches on center?"
- "What would a 400 sq ft stamped patio roughly cost?"
- "It will be 108 F on Saturday in July. Should we still pour, and when?"
Inputs
Ask only for what is missing. Defaults in brackets.
- Shape: slab / driveway / patio, footing, round column, or steps
- Slab: length ft, width ft, thickness in [4; driveways 4-6]
- Footing: total length ft, width in, depth in
- Column: diameter in, height ft, count [1]
- Steps: number of steps, rise in [7], run in [11], width ft
- Waste allowance [10 %]
- Slab extras: rebar spacing in [18], finish broom / colored / exposed / stamped [broom], removing old concrete? [no]
- Pour day: forecast high in F, month
Procedure
- Volume in cubic feet:
- slab: L x W x T / 12
- footing: L x (W / 12) x (D / 12)
- column: 3.14159 x (D / 24)^2 x H x count
- steps (solid, on grade): W x (run / 12) x (rise / 12) x n(n+1)/2
- With waste: V = volume x (1 + waste). Cubic yards = V / 27, rounded to 2 decimals. Order quantity = yards rounded up to the next 0.25 yd.
- Bags (round up): 80 lb = V / 0.60, 60 lb = V / 0.45, 40 lb = V / 0.30. Under 1 cubic yard suggest bags; 1 cubic yard or more suggest ready-mix.
- Rebar grid for a slab at spacing S inches: bars along the length = floor(W x 12 / S) + 1, each L ft; bars along the width = floor(L x 12 / S) + 1, each W ft. Linear feet = sum. 20 ft sticks = ceil(LF x 1.10 / 20). Welded-wire alternative: ceil(area x 1.10 / 50) sheets of 5 x 10 ft.
- Rough installed cost (USD per sq ft): broom 6-10, colored 8-13, exposed aggregate 9-14, stamped 12-20. Above 4 in thick multiply by 1 + 0.10 x (T - 4). Removing old concrete adds 2-4 per sq ft. Round to whole dollars and say it is a planning range, not a quote.
- Pour day from the forecast high:
- under 90 F: low risk, any time, finish before the afternoon peak
- 90-99 F: moderate, start by 7:00 am
- 100-109 F: high, start 5:00-6:00 am and finish by 10:00 am
- 110 F and up: extreme, reschedule if possible; otherwise start at first light and finish by 9:00 am Tips build with the heat: never add water at the truck; at 90+ pre-wet subgrade and forms and have the crew ready; at 100+ ask for a set retarder, keep the mix under 90 F, use shade or windbreaks; at 110+ split the pour. Always start curing right after finishing (curing compound, wet burlap or plastic, moist 7 days). June to September add a monsoon note: watch storm cells, keep plastic on site, route runoff away. Cure schedule: foot traffic after 2 days, vehicles after 7, design strength at 28.
Outputs
A short answer with: cubic feet and yards (with waste), order yards, bag counts, the bags vs ready-mix call, rebar or mesh (slabs), the cost range (slabs), and the pour-day plan if a forecast was given. Show each formula with the user's numbers.
Worked example: 20 x 10 ft slab, 4 in, 10 % waste -> 66.67 ft3 x 1.10 = 73.33 ft3 = 2.72 yd3, order 2.75 yd3; 123 x 80 lb bags; rebar 7 + 14 bars = 280 ft = 16 sticks; broom finish $1,200-$2,000.
Reference
The same formulas ship as packages (npm, PyPI, crates.io, pub.dev, NuGet, RubyGems, Packagist): https://github.com/nbkdevs/concrete-contractors-phoenix
Links
- Concrete driveways, patios, stamped concrete and repairs planned for desert heat: Concrete Contractors Phoenix
- Downloads
- 75All time
- Security audit
- Pass
- Last updated
- 1d ago
- Current version
- v1.0.0
- License
- MIT-0